York Creek/Alpine-Walker Drain Stream Bank Stabilization Project
Alpine-Walker,
MI
Grantee:
Grand Valley State University Water Resources Institute
Basin Program Funds:
$4,382
Non-federal Funds:
$3,120
Project Duration:
11/1997
-
04/1998
Status:
complete
Problem Statement
An increasing percentage of the Alpine-Walker Drainage District is shifting
to high-density, commercial uses with a corresponding increase in impervious
surface areas. These areas lack sufficient storm water control which has resulted
in stream bank failure at several locations in the watershed.
Background
The Alpine-Walker Drain is a feeder stream into the larger York Creek hydrologic
system. Nonpoint source pollution problems and hydrologic instability occurring
in the Drain add to York Creek's problems such as out-of-bank flooding, channel
clogging from imbedded sediment and lateral stream meandering. In order to
address these issues, the York Creek Watershed Project is undertaking a three-track
approach to watershed management which include administrative best management
practices (BMP) such as a township storm water management ordinance, researching
and installing storm water surge control technologies which complement current
storm water systems, and instituting a variety of bio-engineered bank stabilization
activities.
Activities
Phase I: Tree Revetments and Log Wall Construction – Field crews reinforced
slope toes using logs affixed with 3/16 inch steel cable and heavy guage duckbill
driven approximately 2.5 feet into the streambed. Then graduated sizes of
granite cobble were deposited in front and behind the logs, the area immediately
behind the logs was backfilled with finer cobble and clay/sand substrate removed
from the stream channel. Field crews then installed recycled Christmas trees
within the average high water mark in a "shingle" pattern placing larger diameter
trees at the bottom. Several sites required "harder" structures than tree
revetments and field crews installed hardwood log walls behind six-foot steel
posts driven three-feet into the streambed. Large cobble and boulders protected
log walls from high-water then Christmas trees were secured behind the wall
to induce further stabilization. Phase I field work concluded by mid-September
1997.
Phase II: Live Stake Planting – In January 1998 the York Creek
Project Manager decided to supplement Phase I activities with a live stake
planting program. Seven hundred live stakes of species similar to native bush
such as red osier dogwood, grey dogwood, button bush, and black willow were
ordered. Field crews began installing the live stakes in May and completed
the project within two weeks.
Results
The project stabilized approximately 1,000 feet of stream bank during Phase
I. During Phase II 700 native species live stakes were installed as a supplement
to Phase I. An instructional video detailing the Phase II methodology was also
completed.
One year later, 90% of Phase I installations remain
intact. The 10% which required maintenance has been attributed to a
100-year storm event occurring in September 1997. It is estimated that the
project will save 742 tons of soil over fifteen years of the project life.
Local engineering firms have expressed interest in the project
as has the Kent County Drain and Road Commission and Alpine Township. The
York Creek Project Manager presented the project to about 100 people of the
Maple River drainage district and the York Creek Watershed Project Steering
Committee at two workshops and anticipate reaching close to 1,000 more persons
over the next few year. Bio-engineering presents an increasingly accepted
alternative to conventional erosion control practices in stream bank protection
and restoration.
Contact: Ed Frye, (616) 895-3722
|