Duluth-Superior Harbor Dredged Material Management Plan
Introduction
Policy-makers say it. Sportsmen say it. Environmental advocates say
it. Everyone connected to the Great Lakes says it one time or another.
"Lake Superior is different. Lake Superior is unique." And to see how
true this is, all one needs to do is look at all of the programs and
initiatives that seek to preserve the water quality of Lake Superior
or reduce the pollution going into the lake. With all of the attention
focused on protecting Lake Superior, it should come as very little surprise
that there are many stakeholders and many opinions regarding the dredging
strategy for the Duluth-Superior Harbor.
The U.S. Army Corps of Engineers (USACE) completed a Dredged Material
Management Plan (DMMP) for the Duluth-Superior Harbor in April 1999.
For six years, state agencies, local governments, and the Seaway Port
Authority of Duluth reviewed the plan and responded to the Corps of
Engineers about different alternatives available to manage a projected
3 million cubic yards of material over the next 20 years. Through those
years, one central question remained the focus. How to keep the navigation
channels for the largest tonnage Great Lakes port maintained in a cost-effective
manner while adhering to the policies and goals developed to protect
this resource? To answer this question, the stakeholders have put their
trust in communication, creativity and commitment.
No more room at Erie Pier
Since 1979, a large majority (90%) of dredged material from the Duluth-Superior
Harbor has been placed at the Erie Pier Confined Disposal Facility (CDF).
Erie Pier was built like many other CDFs in the Great Lakes under Public
Law 91-611 in the late 1970s. Although initially designed to last for
ten years and store only 1 million cubic yards of material, Erie Pier
has lasted twice as long and stored twice as much material primarily
through raising of the dikes and the recycling of the material for construction
projects. Nevertheless, Erie Pier is finally reaching its capacity and
the USACE needed to develop a management plan to provide for future
dredging and disposal. That management plan is formally known as the
Duluth-Superior Harbor Dredged Material Management Plan (DMMP).
Development of the DMMP
Every port that needs long-term navigational dredging is required
to have a DMMP. The DMMP identifies the dredging needs for a period
of 20 years and method(s) for management of the dredged material. Under
current regulations and procedures, a DMMP's Base Plan needs to adhere
to the "Federal Standard" (33CRF335.7). These regulations clearly state
that the USACE must select those alternatives that are the least costly,
use sound engineering principles, and meet the environmental standards
outlined in Section 404(b)(1) of the Clean Water Act. In the case of
Duluth-Superior Harbor, the USACE-Detroit District indicated from the
beginning of the DMMP process that the Corps needed to develop a Base
Plan consistent with the Federal Standard.
As the development of the DMMP proceeded, it was evident that the Corps
was going to recommend management alternatives that included open water
disposal of dredged material. The open-water alternative included filling
in six deep holes in the St. Louis Bay-harbor area. Although these holes
were not natural, they were recognized as important fishery and benthic
habitats and the States of Minnesota and Wisconsin opposed the filling
of them. While open-water disposal was common up until the 1960s across
the Great Lakes, its use has decreased. Because Minnesota and Wisconsin
are concerned with protecting aquatic habitat, the states developed
enforceable policies that prohibit the in-water disposal of dredged
material unless it is part of a beneficial use project. The deep holes
alternative proposed by the Corps of Engineers did not have any beneficial
use component.
An impasse seemed apparent as both states indicated they would not
be able to issue a Clean Water Act Section 401 water quality certification
to the USACE for the deep hole alternative. Should USACE determine the
deep hole alternative to be the Base Plan, a delay in maintenance dredging
of the harbor could occur once the remaining available space in Erie
Pier CDF was filled, unless the Corps and the states could come to an
agreement for implementation of another dredged material management
alternative.
Exploring Beneficial Use Alternatives
As development of the DMMP proceeded, there was growing interest among
the states to incorporate beneficial use alternatives into the Base
Plan. Those alternatives included habitat creation, mineland reclamation,
beach nourishment, and developing Erie Pier into a dredged material
recycling station. The Corps recognized the importance of protecting
Lake Superior and was supportive of advancing beneficial use alternatives.
However, regulations prevented the Corps of Engineers from incorporating
most of these alternatives into the Base Plan except for beach nourishment
because they did not represent the least costly alternatives. Other
alternatives could be pursued but extra costs may be subject to a cost
share between the federal government and the local sponsor (in this
case, the Seaway Port Authority of Duluth).
Although the DMMP process began to shift more toward beneficial use,
the states remained frustrated. The Port Authority was naturally concerned
about the local match, while the state natural resources and environmental
agencies questioned how federal regulations regarding dredged material
management could in some instances contradict the objectives and the
goals of many federal and international programs designed to protect
the Great Lakes such as the Great Lakes Initiative.
USACE Signs the DMMP with Changes
In April 1999, after the stakeholders reviewed and commented on the
Draft DMMP, the USACE issued a public notice that the DMMP had been
signed. The Corps stated that the Base Plan (which included the deep
hole alternative) would "be used only for the purpose of establishing
the Federal baseline costs for future dredging and placement activities
at Duluth-Superior Harbor." The gist of this public notice was that
the USACE would not pursue the deep hole alternative. However, the Corps
would not have to spend any more money on dredging and disposal in the
Duluth-Superior Harbor than they would have if the deep hole alternative
had been implemented. The USACE also stated in the public notice that
they would further pursue a habitat creation project at the 21st Ave.
West Channel in St. Louis Bay. This habitat creation project would qualify
for funding under Section 204 of The Water Resources Development Act
of 1992 and subject to a 25% local match. The states are beginning to
work together to find that funding, estimated to be $400,000. Therefore,
if the habitat creation project is constructed, then the three alternatives
for managing dredged material for the next twenty years will be:
- Continued Use of Erie Pier until full (2-5 years)
- Beach Nourishment (5 years)
- Habitat Creation at 21st Ave West Channel (10 years)
Also, the USACE and the states are committed to pursuing other beneficial
use alternatives especially processing material at Erie Pier for construction
and other purposes and using dredged material for mineland reclamation
in taconite tailing basins on the Minnesota Iron Range.
Communication + Partnerships = Success
One factor that has made the DMMP process in the Duluth-Superior Harbor
special and unique is the level of communication and the commitment
toward cooperation. The Duluth-Superior Harbor Technical Advisory Committee
(HTAC) has met quarterly for the last fifteen years to discuss maintenance
dredging, the maritime industry, and need for environmental protection
in the Duluth-Superior Harbor. It was through the HTAC meetings that
an open communication link between the states and the USACE was nurtured.
Another effective tool that has produced favorable results is the Duluth-Superior
Harbor Partnering Agreement; a document signed by the key stakeholders.
Initiated by the USACE-Detroit District in 1996, this document outlines
each state agency's commitment to preserving the maritime industry,
protecting the environment and resolving differences in a cooperative
spirit. The Partnering Agreement also asks signatories to make a financial
contribution to support the development and implementation of a work
program. In 1998, $25,000 was raised allowing a regional planning agency
to better facilitate the DMMP process as well as write harbor-related
plans.
Conclusion
Lake Superior is a special and unique freshwater resource. It took
six years to develop a dredging strategy for the Duluth-Superior harbor
with significant give and take among stakeholders. The protracted planning
process and contentiousness of the issues matched what was at stake.
The implementation of the current DMMP will provide for appropriate
maintenance dredging while protecting Lake Superior and the St. Louis
River. Stakeholders have learned that the sun is setting on the old
days of maintenance dredging and disposal and that cooperation and creativity
often produces the best-possible results.
Note: This case study was prepared during the summer of 1999.
For further information:
Andrew Bramson
Transportation Planner
Arrowhead Regional Development Commission
221 West 1st Street
Duluth, MN 55802
Phone: 218-529-7528
E-mail: abramson@mail.ardc.org
Steve Thorp
Great Lakes Commission
Eisenhower Corporate Park
2805 S. Industrial Hwy, Suite 100
Ann Arbor, MI 48104-6791
Phone: 734-971-9135
Fax: 734-971-9150
E-mail: sthorp@glc.org
|