Habitat Restoration in Great Lakes Areas of Concern: Maumee River

NOAA-GLC Regional Habitat Restoration Partnership

Maumee River Project Photos & Videos

Penn 7 Habitat Restoration Photos

Construction begins near the center of the site – September 16,, 2020

Construction begins near the center of the site – September 16,, 2020

Construction begins at the embayment area – September 16, 2020

Construction begins near the connecting channel – September 16, 2020

A water control structure is installed at the end of the connecting channel – October 21, 2020

The embayment dike area is flagged – October 21, 2020

Construction continues on the connecting channel – October 21, 2020

Construction continues on the connecting channel – October 21, 2020

Construction continues on the wetlands area – October 21, 2020

Construction continues on the connecting channel – October 21, 2020

Construction continues on the connecting channel – November 20, 2020

Construction continues on the connecting channel – November 20, 2020

Construction continues on the embayment area – November 20, 2020

Construction continues on the wetland area – November 20, 2020

Construction continues on the connecting channel – November 20, 2020

Construction continues on the embayment dike – December 17, 2020

Construction continues on the embayment dike – December 17, 2020

A culvert is installed at the water embayment dike – March 8, 2021

A culvert is installed at the water embayment dike – March 8, 2021

Construction continues on the connecting channel – June 7, 2021

Construction continues on the connecting channel to the embayment area – June 7, 2021

The embayment dike is completed – June 7, 2021

Plantings take place throughout the site – June 7, 2021

Plantings take place throughout the site – June 7, 2021

Final changes are made to a water control structure near the wetland area – June 7, 2021